This is a brand new school, where everything is supposed to be perfect. The contractor thinks, evidently, it is no big deal that the floors, the cement floors, have hills and valleys and an actual pothole.
I have been in the school, before the first walkthrough, and thought that there was going to be some final, and leveling, layer of cement poured to level everything and cover the hole. Who leaves a two foot across hole in the floor of a new building, and expects it to pass inspection? It wasn't even in an out of the way place, but in the MIDDLE of the main hallway!
Oh, yeah, all desks had already been moved out of the old building into another school to replace old and wornout desks there. Can anyone say 'fiasco'?
|